Goyder River Crossing

Client: Department of Infrastructure

Project: Goyder River Crossing

Project Overview:The project is located some 450km East of Katherine where there are three bridges to be constructed including 12km of road realignment.

Contractor: Norbuilt

Project Start Date: May 2013

Estimated Completion Date: May 2014

Value Add & Services provided by HiQA:

Conformance testing in particular concrete for bridges, compaction conformance for bridge abutments and new alignment